Astor House Construction Update: 10/20/16

Exciting progress today with the removal of shoring from the first and second floors! Loads have now been transferred to the new beams and columns. Finishing work is now underway including installing base plates to existing walls, bolting lapped joists, and re-installing furnace and pipes just in time for cooler weather!

 